Since 2008
Based in Belgium and France
+ 60 000 clients
Our blog
A.S.S.
Shopping Cart
Comprehensive technical guide to Deye hybrid inverter configuration: energy bus architecture, critical BMS...
Découvrez comment la tarification dynamique et le tarif Impact ORES transforment la rentabilité du stockage d'énergie...
Guide complet pour configurer un onduleur DEYE triphasé sur réseau 3x230V sans neutre (IT) en Belgique. Procédure de...
Discover photovoltaics from A to Z: operation, components, installation and profitability. An accessible guide to...
Décryptez les unités électriques essentielles du photovoltaïque : ampères, volts, watts, kWc, kWh, VA. Explications...
The Deye hybrid inverter (covering the single-phase SUN-3K to 8K-SG04LP1-EU ranges and their three-phase equivalents) should not be considered as a simple DC-to-AC converter. From a system engineering perspective, it is a decentralised microgrid controller capable of orchestrating complex energy flows between multiple sources and loads.
"Unlike conventional string inverters, which operate according to a unidirectional logic – from the panels to the grid – Deye's hybrid architecture is based on matrix management of energy flows."
💡 Recommended inverter: Deye 5 kVA SUN-5K-SG03LP1-EU single-phase hybrid inverter
Complete solution with intelligent battery management and integrated backup function
The hardware architecture of the inverter is based on several separate voltage buses, whose interaction is governed by software parameters that we will analyse later. Understanding these buses is essential to understanding the physical implications of the digital settings.
First, the High Voltage DC Bus is the entry point for photovoltaic energy. The MPPT (Maximum Power Point Tracking) trackers connected to this bus adjust the input impedance to extract maximum power from the PV module strings. According to the manual, the MPPT voltage range generally extends from 150V to 425V. Incorrect configuration of the PV strings that would fall outside this range would render the MPPT algorithms ineffective, regardless of the inverter's software settings.
Secondly, the Low Voltage DC Bus (48V) is the critical interface with electrochemical storage. This is a unique design feature of Deye residential inverters (unlike high voltage systems such as HV). This bus typically operates between 40V and 60V. Conversion between the High Voltage Bus (PV) and the Low Voltage Bus (Battery) involves bidirectional DC-DC converters (Buck-Boost), whose efficiency and safety depend directly on the current and voltage parameters defined in the "Battery Setting" menu.
Thirdly, the AC bus is physically segmented into three separate ports, each with a specific role and electrical behaviour defined by the firmware:
The GRID Port: This is a bidirectional interface synchronised with the public grid. It is through this port that the inverter imports missing energy or exports surpluses. Its management is subject to strict grid codes to ensure the safety and stability of the public grid.
The LOAD Port (Backup/UPS): This port is designed to operate in "island" mode. When the grid is present, it is powered via a bypass relay. In the event of a power cut, the inverter switches over in a few milliseconds (usually less than 10 ms, although this can be adjusted using the "Backup Delay" setting) to generate its own voltage and frequency.
The GEN Port (Smart Port): This is undoubtedly the most versatile interface in the Deye ecosystem. Electrically, it is a programmable auxiliary AC port capable of functioning either as an input (for a generator or micro-inverter) or as an output (for offloading non-critical loads).
The intelligence of the system, and therefore the purpose of this configuration guide, lies in the user's ability to define the logical rules that govern the transfer of energy between these physical nodes. A poor understanding of this architecture invariably leads to sub-optimal configurations, where the inverter "fights" against its own parameters, for example by charging the battery from the grid when solar power is available, or by cutting off power to critical loads due to a lack of defined priority.
Before even addressing the software interface, it is imperative to understand that certain parameters of the Deye are dictated by the physical realities of the installation. The software cannot compensate for hardware deficiencies, but it must be configured to respect the physical limitations of the installed components.
The user manual provides precise tables regarding the required cable sections. These physical specifications have a direct impact on the "Max Charge/Discharge Current" settings in the battery menu. For a 5kW or 6kW model, the currents on the battery side can reach considerable values, up to 135A for the 6kW model.
It is common to see installations wired with 25mm², which is physically capable of carrying approximately 100A over short distances. However, if the installer leaves the default setting of 135A in the software, there is a risk of excessive cable heating under maximum load.
⚠️ CRITICAL RULE: The software configuration must accurately reflect, or even be conservative, in terms of the physical capacity of the conductors. If the wiring is rated for 100A, the "Max Discharge Current" software setting must never exceed this value, regardless of the theoretical capacity of the battery or inverter. Ignoring this correlation between copper and the code is a common cause of premature ageing of insulation and thermal protection tripping.
Similarly, on the AC side, the Grid and Load connections require 6mm² (AWG 8) cables for 3.6kW to 6kW models, with recommended 40A circuit breakers. The setting of export or import power limits ("Grid Peak Shaving") must take into account the rating of these protections. If the upstream circuit breaker is 32A, configuring the inverter to draw 40A from the grid (to charge the battery and power the house simultaneously) will inevitably cause a power cut due to the physical circuit breaker tripping.
The operation of the "Zero Export" and "Solar Sell" modes relies entirely on the accuracy of the measurements provided by external current transformers (CTs) or smart meters. The inverter acts as a slave system: it measures the flow at the grid connection point and adjusts its power to reach a setpoint (usually zero watts).
A common physical error is incorrect positioning or reversal of the CT direction. The manual states that the arrow on the CT must point towards the inverter (or towards the load, depending on the specific model convention, often towards the inverter/house). If this sensor is physically reversed, the inverter will interpret consumption as injection (and vice versa). In the software, this results in erratic behaviour: the more the house consumes, the more the inverter reduces its power to "stop exporting", or conversely, it can overload the system by injecting massively to compensate for "negative injection". Although the software sometimes allows the reading to be reversed via a parameter, good engineering practice requires correct physical installation to ensure the consistency of the data displayed.
Deye 6 kVA hybrid inverter with advanced energy flow management
The inverter settings can be accessed viathe integrated LCD touch screen. This interface is the gateway to the "brain" of the system. Navigation usually starts with the gear icon, which opens the "System Setup" menu.
In the "Basic Setting" menu, setting the time and date may seem trivial, but it is of paramount importance in an energy management system. The Deye inverter relies on its internal clock (RTC - Real Time Clock) to execute "Time of Use" (TOU) strategies.
"It has been reported by the technical community that the internal RTC clock of some Deye models can experience significant time drift, sometimes by several minutes per day. If this drift is not corrected, it will gradually shift the charging and discharging time slots. After a few weeks, the inverter may start charging the battery from the grid at 8:00 a.m. (full rate) thinking that it is still 5:00 a.m. (off-peak rate)."
To overcome this hardware problem, it is strongly recommended to use the "Time Sync" function if the inverter is connected to the Internet via the Wi-Fi dongle. This function forces the inverter to synchronise its clock with the Solarman/Deye cloud NTP server, ensuring that the execution of energy profiles remains aligned with the electricity supplier's actual tariffs. In addition, accurate time stamping is essential for post-mortem analysis of incidents via error logs (Event Logs).
The Deye operating system prioritises access to settings via different security codes that are crucial to know for maintenance:
Although less critical to system security, these settings improve the user experience and daily maintenance:
The "Battery Setting" menu is the nerve centre of autonomy management. The configuration of this section determines the battery life, the efficiency of the system and its ability to respond to power demands. An error here is often the root cause of premature failures or unexpected blackouts despite an apparently charged battery.
The first fundamental choice is found in the "Batt Mode" tab. The installer must choose between digitally controlled management ("Lithium") or analogue voltage-based management ("Use Batt V" or "Use Batt %").
Lithium Mode (BMS): This is the industry standard for modern LiFePO4 batteries (Pylontech, Dyness, Deye SE, etc.). By selecting this mode and the appropriate protocol code (e.g. 00, 12), the inverter relinquishes some of its decision-making autonomy in favour of the battery's BMS (Battery Management System). Via the CAN or RS485 cable, the BMS communicates its constraints in real time: "Charge me to a maximum of 53.2V", "Do not exceed 25A charging current because I am cold", or "Stop everything, a cell is out of balance". In this mode, manual voltage settings (Float, Absorption) become secondary or are greyed out, as the inverter obeys the dynamic values sent by the BMS.
Voltage Mode (Use Batt V): This mode is essential for lead-acid batteries (AGM, Gel) and for "DIY" or older generation lithium batteries without smart communication. Here, the inverter becomes the sole master on board. It must estimate the SOC based solely on the voltage at the battery terminals.
⚠️ IMPEDANCE TRAP: The major problem with this mode with lithium is the very flat discharge curve of LiFePO4 (the voltage varies very little between 20% and 80% charge). In addition, under heavy load (e.g. 100A), the voltage drops artificially due to internal resistance and cable resistance (Voltage Sag). The inverter may read "46V" and trigger an emergency shutdown ("Low Batt Cut-off") when the battery is still at 40% of its actual charge. This is why, in voltage mode, it is crucial to set very conservative cut-off thresholds to avoid untimely shutdowns under load.
💡 BMS-compatible batteries: Complete range of Pylontech LiFePO4 batteries
48V storage solutions with CAN/RS485 communication for Deye inverters
The "Max A Charge" and "Max A Discharge" parameters define the energy "taps". They must be configured taking into account the lowest constraint among three factors:
A best practice rule for the longevity of lithium batteries is not to exceed a continuous discharge rate of 0.5C (i.e. 50A for a 100Ah battery), even if the technical data sheet allows 1C. Setting the "Max A Charge" to too high a value can stress the cells and cause BMS disconnections due to overcurrent. Conversely, setting the value too low will limit the system's ability to absorb a peak in solar production, thus wasting free energy.
Three parameters define the behaviour of the system at the end of autonomy: "Low Batt", "Shutdown", and "Restart". Confusion between these terms is common, but distinguishing between them is vital for system resilience.
Low Batt (Grid Preservation Threshold): This parameter (expressed in % or V) defines the level below which the inverter stops using the battery for self-consumption when the grid is present. It is a strategic reserve. If you set it to 20%, the inverter will use the battery up to 20%, then switch to the grid to power the house, keeping the remaining 20% "on standby" for a possible power cut.
Shutdown (Survival Threshold): This parameter is the absolute limit in off-grid mode. If a power failure occurs and the battery drains to this threshold (e.g. 10% or 15%), the inverter completely cuts off the AC output (total blackout) to save the battery from destructive deep discharge. It is imperative that Shutdown is strictly lower than Low Batt.
Restart: After a "Shutdown" event, the inverter is turned off (AC side), but its solar charger remains active. As soon as the sun returns, the battery recharges. The "Restart" parameter defines the level (e.g. 30% or 40%) at which the inverter agrees to turn the AC output back on.
Importance of Hysteresis: Never set "Restart" too close to "Shutdown". If Shutdown is set to 15% and Restart to 16%, the system may oscillate (start/stop) at sunrise: it restarts at 16%, a load (fridge) turns on, the voltage drops, it falls below 15% and cuts out, etc. A margin of 15% to 20% is recommended to ensure a stable restart.
In the "Batt Set 2" tab (or integrated into the "Time of Use" table depending on the firmware version), the user decides which sources are authorised for recharging.
Grid Charge: By default, this option should be disabled to maximise solar self-consumption. Enabling "Grid Charge" means allowing the purchase of electricity to fill the battery. However, in a tariff arbitrage strategy (purchase during off-peak hours, use during peak hours), this function is essential when coupled with the timer.
Gen Charge: This setting allows the inverter to use energy from the GEN (Generator) port to charge the battery. It is accompanied by a specific current setting (Amps). This is a critical point for generator protection: a generator should not be charged to 100% suddenly. It is advisable to limit the "Gen Charge" charging current to a value which, when added to the consumption of the house, does not exceed 70-80% of the generator's rated power to prevent the engine from stalling.
The installer defines the macroscopic strategy for the installation in the "System Work Mode" menu. This is where you determine whether the system should maximise autonomy, maximise financial savings, or behave as a simple backup system. The nuances between the modes are subtle but have major financial impacts.
Selling First mode is designed for markets where buying back electricity is economically advantageous (high feed-in tariff) or for systems without significant storage. In this mode, the priority logic is as follows:
The user can limit this injection via the "Max Sell Power" parameter. For example, if the connection contract limits injection to 3kW on a 5kW inverter, it is essential to adjust this parameter to avoid penalties from the grid operator.
For the majority of residential users seeking energy independence without a sales contract, "Zero Export" modes are the norm. However, there is a fundamental distinction between two variants:
Zero Export to Load: This mode is often a source of disappointment. When selected, the inverter only monitors consumption on its "Load" (Backup) port. It completely ignores what is happening in the rest of the house (on the main board). The inverter will therefore produce just enough for the fridge and emergency lights, and charge the battery. If the water heater is connected to the main panel, the inverter will not produce power for it, even if the batteries are full and the sun is shining. This mode is a fallback solution if no current sensor (CT) is installed.
Zero Export to CT (The Standard): This is the optimal mode for an entire house. The inverter uses the current transformer (CT) installed just after the main meter to measure the total consumption of the house (backup loads + non-backup loads). The control algorithm attempts to cancel out the consumption measured by the CT by injecting the exact power into the Grid port.
Interaction with Solar Sell: A very popular configuration is to enable "Zero Export to CT" and check the "Solar Sell" box. This creates a hybrid logic: the inverter compensates for the entire house, charges the batteries, and if there is still solar power left, it injects it into the grid (up to the Max Sell Power limit). This is the 'all-in-one' setting that maximises solar usage."
This binary setting changes the destination of the first solar watt produced in the morning.
The "Time of Use" table is a fine-tuning management tool that allows you to override the default logic. It divides the day into six time slots. For each slot, three key parameters interact:
Power (Watts): Contrary to popular belief, this is not the charging power, but often the maximum discharge power allowed during that time slot.
Batt (SOC %): This is the most misunderstood parameter. It does not mean "Charge to X%". It means "Do not let the SOC fall below X% as long as the grid is present".
Grid Charge: This is explicit authorisation to use the grid to reach the SOC setpoint for the range. This is essential for charging at night during off-peak hours (e.g. 2 a.m. to 6 a.m., SOC 80%, Grid Charge ON).
Frequent confusion arises from the PC interface (Solarman), which often places the checkboxes for the days of the week (Monday, Tuesday, etc.) on the "System Work Mode 1" page, whereas in the manual and on the inverter screen, this function is called "Work Mode 4".
The Logic: Checking a day means "Apply the TOU table on that day". Unchecked days: If you do not check Sunday, for example, the TOU (Time of Use) programme is disabled for the entire day on Sunday. The inverter then reverts to the general strategy defined in "System Work Mode 1" (e.g. Zero Export to CT + Load First). It will charge the battery as soon as there is sunlight and discharge it as soon as there is demand, without any time constraints or forced minimum SOC threshold (other than the overall "Low Batt" safety threshold).
The "GEN" port is a technical feature that sets Deye apart from many of its competitors. It is not a simple passive input, but a bidirectional port that can be programmed via the "Gen Port Use" menu. It can adopt three distinct, mutually exclusive identities.
This is the port's native function. It allows a generator to be connected as a tertiary backup source (after solar and battery). The inverter manages not only the power, but also the start-up of the generator via its dry contacts (labelled G -Start/G-Valve, or Grid Signal/Gen Signal). The "Gen Force" function, when activated, allows the generator to be started regardless of standard conditions.
System engineering requires particular attention to dimensioning here: if the "Generator Input Rated Power" parameter is set too high, the inverter may request a sudden load that will cause the generator to stall (transient overload phenomenon). 🔗 Generator guide
In this mode, the GEN port changes direction: it becomes an AC output capable of powering "dump" or non-critical loads, such as a resistance water heater or a swimming pool pump. The intelligence lies in the configurable activation conditions:
The "On Grid Always On" option: This subtle setting allows this output to be powered continuously when the grid is available, and only switches to "smart load shedding" mode (conditional) during power cuts. This ensures that hot water is available even when it is cloudy, as long as the grid is working.
This advanced mode allows an existing solar inverter (or micro-inverters) to be coupled to the GEN port. The energy fed in by these third-party inverters is aggregated by the Deye, which can use it to charge the batteries or power the Load output.
The technical challenge of this mode is managing overload in off-grid mode (Island Mode). If the grid goes down, the battery is full and the micro-inverters are producing at full capacity, the energy has nowhere to go. The Deye cannot communicate digitally with a third-party inverter to tell it to reduce its output. It therefore uses a universal physical trick: Frequency Shifting.
The Deye increases the frequency of the microgrid it generates (from 50.0Hz to 51Hz, 52Hz, etc.). The "AC Couple Fre High" parameter defines the target frequency for total shutdown. The micro-inverters, detecting this abnormal frequency (according to their internal VDE standard), reduce their power (Droop mode) or shut down completely. This is a robust but brutal regulation mechanism. Incorrect configuration of this threshold (e.g. set too low) can prevent the micro-inverters from operating, or conversely (set too high) prevent them from shutting down and cause a dangerous DC overvoltage for the batteries.
The inverter interacts with the public grid, which imposes strict safety constraints to protect property and people.
The "Grid Mode" parameter is not a mere administrative formality. It loads a complex set of parameters (voltage thresholds, disconnection times, power ramps) that comply with local legislation. Using "General Standard" instead of the specific standard (e.g. VDE 0126, EN 50549) can make the installation non-compliant and dangerous for network technicians (risk of undetected islanding).
In addition, some standards activate specific functions such as "Self-Check" for the Italian standard CEI 0-21, which launches an automated test procedure for protection relays (password to launch the test: 1234).
In TT or TN neutral systems, the neutral is connected to earth at the public transformer. During a grid outage, the inverter opens its relays to isolate itself (Island Mode). In doing so, it also cuts the link to the supplier's earth. The "Load" output is then in IT (floating neutral) or undefined mode. In this state, the 30mA residual current circuit breakers in the house can no longer correctly detect current leaks, creating a deadly hazard.
⚠️ CRITICAL SAFETY: The "Signal Island Mode" function is Deye's response to this problem. When activated, the inverter sends a signal (on a dedicated port or via an internal relay for three-phase units) as soon as it switches to island mode. This signal must drive an external power contactor (often called a neutral earthing contactor) that physically connects the Neutral and Earth on the Load side. This restores a temporary TN-S system, allowing the residual current devices to function. This setting must be configured in consultation with a qualified electrician, as a wiring error here can cause a short circuit when the grid returns.
Photovoltaic fires are often caused by series electric arcs (poor contact in an MC4 connector). Recent Deye inverters incorporate a software AFCI (Arc Fault Circuit Interrupter) function.
By activating "Solar Arc Fault ON" in the Advanced menu, the digital signal processor (DSP) continuously analyses the frequency spectrum of the DC current. If it detects the characteristic signature (electrical "noise") of an arc, it instantly cuts off the MPPT stage. This is a passive safety feature that costs nothing to activate but can save the building.
This function is a load management tool. It allows you to set a limit on the power imported from the grid (e.g. 6000W). If the house's consumption exceeds this threshold (e.g. if all the electric heating is turned on), the inverter will make up the difference by drawing on the battery, acting as a "turbo" for the grid.
This allows you to subscribe to an electricity plan that is lower than the actual peak power of the house, or to avoid tripping the main circuit breaker during consumption peaks.
Even with a perfect configuration, unforeseen events can occur. The Deye interface provides essential diagnostic tools.
Error codes are not random; they often point to configuration inconsistencies:
Deye's firmware is constantly evolving. Features such as improved MPPT management and Time of Use fixes are deployed via updates. It is recommended to check the versions (HMI/Main) via the "Device Info" screen and to perform updates via the Wi-Fi dongle if any instability is noted.
"Configuring a Deye hybrid inverter is a balancing act between physics, safety and economics. Each parameter, from simple time settings to complex Frequency Shifting thresholds, interacts with the others to form a coherent ecosystem. A successful installation is measured not only by the solar production displayed, but also by the stability of the system during transitions (grid outages, cloudy periods) and the long-term health of the batteries. By following the "Physics first, Software second" logic detailed in this report, the user transforms their inverter from a simple electronic box into a truly intelligent and sustainable energy manager. »
Check these 5 critical points: 1) Time Sync enabled to prevent TOU time drift, 2) Max Charge/Discharge Current ≤ wiring limit (e.g. 100A for 25mm²), 3) Lithium mode (BMS) enabled for modern batteries with 00 or 12 protocols, 4) CT correctly oriented (arrow pointing towards inverter/house), 5) Hysteresis 15-20% between Shutdown and Restart. Consult the "System Info" screen to validate the active parameters.
"Zero Export to Load" ONLY manages loads connected to the inverter's Backup port (backup loads). It ignores the rest of the house. "Zero Export to CT" manages the ENTIRE house by measuring via the current transformer installed at the main meter (backup + non-backup loads). For optimal self-consumption throughout the home, always use "Zero Export to CT" with a correctly installed CT.
This is the "Voltage Sag" phenomenon. In voltage mode (Use Batt V), under heavy load (e.g. 100A), the terminal voltage drops artificially due to the internal resistance of the battery and cables. The inverter reads a low voltage (e.g. 46V) and triggers the "Low Batt Cut-off" protection. Solutions: 1) Switch to Lithium mode (BMS) for accurate SOC measurement via CAN/RS485 communication, 2) Increase cable cross-section (25mm² → 35mm²), 3) Lower Max Discharge Current, 4) Set Low Batt lower (but be careful with battery safety, do not go below 10-15%).
No, the GEN port is multifunctional but EXCLUSIVE. You must choose ONE function from the "Gen Port Use" menu: either Generator Input, Smart Load Output, or Micro Inv Input (AC Coupling). To have both a generator AND load shedding simultaneously, you need an installation with specific external wiring and manual switching via contactors, or you can opt for an inverter model with separate dedicated ports.
Example of a typical Belgian tariff (10 p.m.-7 a.m. off-peak hours): Range 1 (12 a.m.-7 a.m.): SOC 90%, Grid Charge ON, Power 5000W → charges the battery from the grid during off-peak hours. Range 2 (07:00-22:00): SOC 20%, Grid Charge OFF, Power 5000W → uses battery for self-consumption up to 20%, then switches to grid. Range 3 (22:00-23:59): SOC 90%, Grid Charge ON, Power 5000W → recharges at the start of off-peak hours. Tick all days of the week in "Work Mode 4" for continuous activation. For weekends without TOU: untick Saturday/Sunday.
With an optimal configuration (BMS enabled, currents limited to 0.5C, SOC maintained between 20-90%, temperature controlled at 15-25°C), LiFePO4 batteries (Pylontech, Dyness, Deye SE) achieve 6000-8000 cycles at 80% DOD (Depth of Discharge), or approximately 15-20 years of residential use with 1 cycle/day. Incorrect configuration (voltage mode with voltage sag, rapid overcharging/discharging >1C, regular deep discharges <10%, extreme temperatures) can drastically reduce this lifespan to only 5-7 years.
Wattuneed SPRLRue Henripré 12, 4821 Andrimont, BelgiumTel: +32 87 45 00 34 – info@wattuneed.comwww.wattuneed.com | Technical support
check_circle
This store asks you to accept cookies for performance, social media and advertising purposes. Social media and advertising cookies of third parties are used to offer you social media functionalities and personalized ads. Do you accept these cookies and the processing of personal data involved?